by JBMoore » Mon Dec 24, 2018 9:19 am
It's been done several ways. Sheet 24 of the CB-1 plans shows the details, which is the way I did it. Sheet 23 shows the wire lengths.
The CB-1 is a copy of the J-3 Cub system. An inner bushing, with two outer bushings, at the hinge location. The attach bolt goes through a bushing in the stabilizer spar centered on the hinge.
From John's picture, it looks like he used the strap method where a u-shaped strap goes around the elevator/rudder spars with an attach bolt in the stabilizer spar.
In either case, the attach point is centered on the hinge.
The lower attach point is a strap, across both longerons, centered on the bolt hole that attaches the tail spring.
Jeff Moore
It's been done several ways. Sheet 24 of the CB-1 plans shows the details, which is the way I did it. Sheet 23 shows the wire lengths.
The CB-1 is a copy of the J-3 Cub system. An inner bushing, with two outer bushings, at the hinge location. The attach bolt goes through a bushing in the stabilizer spar centered on the hinge.
From John's picture, it looks like he used the strap method where a u-shaped strap goes around the elevator/rudder spars with an attach bolt in the stabilizer spar.
In either case, the attach point is centered on the hinge.
The lower attach point is a strap, across both longerons, centered on the bolt hole that attaches the tail spring.
Jeff Moore